Project Start Date: Tue 9/5/06
Project Finish Date: Fri 1/26/07
Name | Resource_Names | Duration | Finish_Date |
|---|---|---|---|
Phase 1: Preparation and Planning | 93.25 days | Fri 1/12/07 | |
Agree Scope and Steps | PM,PE,US Mgmt,China Mgmt | 1 day | Tue 9/5/06 |
Project Schedule | PM,PE,US Mgmt,China Mgmt | 1 day | Wed 9/6/06 |
Resources | PM,PE,US Mgmt,China Mgmt | 1 day | Thu 9/7/06 |
Technology Infrastructure | 5 days | Mon 9/11/06 | |
Review technical support arrangements in China | IT,GTS,China Ops | 5 days | Mon 9/11/06 |
Review Internet connections | IT,GTS,China Ops | 5 days | Mon 9/11/06 |
Project Management | 85.25 days | Fri 1/12/07 | |
Review Meeting | PE,PM,US Mgmt | 2 hrs | Fri 9/15/06 |
Review Meeting | PE,PM,US Mgmt | 2 hrs | Fri 9/29/06 |
Review Meeting | PE,PM,US Mgmt | 2 hrs | Fri 10/13/06 |
Review Meeting | PE,PM,US Mgmt | 2 hrs | Fri 10/27/06 |
Review Meeting | PE,PM,US Mgmt | 2 hrs | Fri 11/10/06 |
Review Meeting | PE,PM,US Mgmt | 2 hrs | Fri 11/24/06 |
Review Meeting | PE,PM,US Mgmt | 2 hrs | Fri 12/8/06 |
Review Meeting | PE,PM,US Mgmt | 2 hrs | Fri 12/29/06 |
Review Meeting | PE,PM,US Mgmt | 2 hrs | Fri 1/12/07 |
Report writing (Research and deploy) | 3 days | Thu 9/14/06 | |
Writing tools | IT | 1 day | Tue 9/12/06 |
Resources (internal and/or external) | US Mgmt,IT | 1 day | Tue 9/12/06 |
Delivery mechanism (technology/infrastructure) | IT | 3 days | Thu 9/14/06 |
On-going administration | IT | 1 day | Tue 9/12/06 |
Phase 2: Application Implementation | 103.5 days | Fri 1/26/07 | |
Material Library | 38 days | Thu 10/26/06 | |
Training on material library features | China Mgmt,China Ops,US Mtlrls | 0.5 days | Tue 9/5/06 |
Agree materials procedures | 4.5 days | Mon 9/11/06 | |
Agree what information should be stored | China Mgmt,China Ops,US Mtlrls | 0.5 days | Tue 9/5/06 |
Agree procedures for materials status | China Mgmt,China Ops,US Mtlrls | 1 day | Wed 9/6/06 |
Agree procedures for committing new materials | China Mgmt,China Ops,US Mtlrls | 1 day | Thu 9/7/06 |
Vendor Management: procedures/reports | China Mgmt,China Ops,US Mtlrls | 1 day | Fri 9/8/06 |
Document procedures for US and China offices | PM | 1 day | Mon 9/11/06 |
Tools to support agreed procedures | 28 days | Thu 10/12/06 | |
Review GTS Leather subsystem | China Mgmt,China Ops,US Mtlrls | 1 day | Tue 9/5/06 |
Fix New Material Report so it is useful | GTS,US Mtrls | 1 day | Tue 9/5/06 |
Write other new operational reports as required | IT | 20 days | Thu 10/12/06 |
Conversion | 3.75 days | Fri 9/15/06 | |
Clean up old materials in database | US Mtlrls,China Ops,China Mgmt,GTS | 3.75 days | Fri 9/15/06 |
Input new materials | China Ops | 3 days | Thu 9/14/06 |
Input vendor information | China Ops | 1 day | Tue 9/12/06 |
Reports | 10 days | Thu 10/26/06 | |
Review management requirements | IT,US Mtrls,China Mgmt,China Ops | 5 days | Thu 10/19/06 |
Write reports | IT | 5 days | Thu 10/26/06 |
Product Manager | 61 days | Tue 11/28/06 | |
Overview and Training | PM,PE,US PD,GTS,IT | 0.5 days | Tue 9/5/06 |
Usability session (US PD) | 10 days | Mon 9/18/06 | |
Updating | 10 days | Mon 9/18/06 | |
Review | GTS,US PD | 2 days | Wed 9/6/06 |
Compare to Excel | GTS,US PD | 1 day | Thu 9/7/06 |
Suggestions for improvement | GTS,US PD | 1 day | Fri 9/8/06 |
Required changes | GTS,US PD | 1 day | Mon 9/11/06 |
Modify PM as required | GTS | 5 days | Mon 9/18/06 |
Output | 7 days | Wed 9/13/06 | |
Review printed output | GTS,US PD | 2 days | Wed 9/6/06 |
Document requirements for printed output | GTS,US PD | 2 days | Fri 9/8/06 |
Modify printed output to requirements | GTS | 3 days | Wed 9/13/06 |
Usability session (China PD) | 10 days | Mon 10/2/06 | |
Updating | 10 days | Mon 10/2/06 | |
Review | GTS,US PD | 2 days | Wed 9/20/06 |
Compare to Excel | GTS,US PD | 1 day | Thu 9/21/06 |
Suggestions for improvement | GTS,US PD | 1 day | Fri 9/22/06 |
Required changes | GTS,US PD | 1 day | Mon 9/25/06 |
Modify PM as required | GTS | 5 days | Mon 10/2/06 |
Output | 7 days | Wed 9/27/06 | |
Review printed output | GTS,US PD | 2 days | Wed 9/20/06 |
Document requirements for printed output | GTS,US PD | 2 days | Fri 9/22/06 |
Modify printed output to requirements | GTS | 3 days | Wed 9/27/06 |
Message Center | 2 days | Wed 10/4/06 | |
Review Message Center for usefulness | US PD,China Ops | 2 days | Wed 10/4/06 |
License Message Center if required | 0 days | Wed 10/4/06 | |
Operating Procedures for Product Manager | 13 days | Mon 10/23/06 | |
Review modifications to UI and Documents | US PD,China Ops,PM,GTS | 2 days | Fri 10/6/06 |
Map and document process flow | US PD,China Ops,PM,GTS | 4 days | Thu 10/12/06 |
China and US sign off on responsibilities. | US PD,China Ops | 0 days | Thu 10/12/06 |
Document procedures | PM | 5 days | Thu 10/19/06 |
Sign off on documentation | US PD,China Ops | 0 days | Thu 10/19/06 |
Training | PM | 2 days | Mon 10/23/06 |
Conversion | 5 days | Mon 10/30/06 | |
Review any conversion of existing Specs | US PD,China Ops,PM,GTS | 3 days | Thu 10/26/06 |
Perform conversion | GTS | 2 days | Mon 10/30/06 |
Reports | 13 days | Thu 11/16/06 | |
Review KPI and reporting requirements | PE,PM,US PD,RW | 3 days | Thu 11/2/06 |
Write reports | RW | 10 days | Thu 11/16/06 |
Extending usage | 3 days | Tue 11/21/06 | |
Belts | 2.5 days | Tue 11/21/06 | |
Review existing information from GTS against new procedures | US PD,PM | 2.5 days | Tue 11/21/06 |
Apparel | 2.5 days | Tue 11/21/06 | |
Review existing information from GTS against new procedures | US PD,PM | 2.5 days | Tue 11/21/06 |
Accessories | 3 days | Tue 11/21/06 | |
Prepare overview on using SoftShoe for accessories | GTS | 3 days | Tue 11/21/06 |
Review matrerial | US PD,PM | 1 day | Fri 11/17/06 |
Change Manager | 2 days | Thu 11/23/06 | |
Review Change Manager for usefulness | US PD,China Ops | 2 days | Thu 11/23/06 |
License Change Manager if required | 0 days | Thu 11/23/06 | |
Implementation and Training | PM,GTS,China Ops,US PD | 3 days | Tue 11/28/06 |
Sample Manager | 26 days | Tue 11/7/06 | |
Overview and Training | PM,PE,US PD,GTS,IT | 0.5 days | Tue 10/3/06 |
Usability session (US PD) | 7 days | Wed 10/11/06 | |
Updating | 5 days | Mon 10/9/06 | |
Review | GTS,US PD | 1 day | Tue 10/3/06 |
Suggestions for improvement | GTS,US PD | 1 day | Wed 10/4/06 |
Required changes | GTS,US PD | 1 day | Thu 10/5/06 |
Modify Sample Manager as required | GTS | 2 days | Mon 10/9/06 |
Output | 7 days | Wed 10/11/06 | |
Review printed output | GTS,US PD | 2 days | Wed 10/4/06 |
Document requirements for printed output | GTS,US PD | 2 days | Fri 10/6/06 |
Modify printed output to requirements | GTS | 3 days | Wed 10/11/06 |
Usability session (China PD) | 11 days | Thu 10/26/06 | |
Updating | 11 days | Thu 10/26/06 | |
Review | GTS,US PD | 4 days | Tue 10/17/06 |
Suggestions for improvement | GTS,US PD | 1 day | Wed 10/18/06 |
Required changes | GTS,US PD | 1 day | Thu 10/19/06 |
Modify Sample Manager as required | GTS | 5 days | Thu 10/26/06 |
Output | 7 days | Fri 10/20/06 | |
Review printed output | GTS,US PD | 2 days | Fri 10/13/06 |
Document requirements for printed output | GTS,US PD | 2 days | Tue 10/17/06 |
Modify printed output to requirements | GTS | 3 days | Fri 10/20/06 |
Operating Procedures for Sample Manager | 13 days | Thu 10/19/06 | |
Review modifications to UI and Documents | US PD,China Ops,PM,GTS | 2 days | Wed 10/4/06 |
Map and document process flow | US PD,China Ops,PM,GTS | 4 days | Tue 10/10/06 |
China and US sign off on responsibilities. | US PD,China Ops | 0 days | Tue 10/10/06 |
Document procedures | PM | 5 days | Tue 10/17/06 |
Sign off on documentation | US PD,China Ops | 0 days | Tue 10/17/06 |
Training | PM | 2 days | Thu 10/19/06 |
Reports | 13 days | Tue 11/7/06 | |
Review KPI and reporting requirements | PE,PM,US PD,RW | 3 days | Tue 10/24/06 |
Write reports | RW | 10 days | Tue 11/7/06 |
Implementation and Training | US PD,China Ops,PM | 3 days | Fri 11/10/06 |
Style Adoption / Commercialization | 54.5 days | Fri 1/26/07 | |
Review existing GTS Software | 21 days | Mon 12/11/06 | |
Line Manager | 10 days | Fri 11/24/06 | |
Usability session (US PD) | 5 days | Fri 11/17/06 | |
Updating | 5 days | Fri 11/17/06 | |
Review | GTS,US PD | 1 day | Mon 11/13/06 |
Suggestions for improvement | GTS,US PD | 1 day | Tue 11/14/06 |
Required changes | GTS,US PD | 1 day | Wed 11/15/06 |
Modify as required if accepted | GTS | 2 days | Fri 11/17/06 |
Output | 4 days | Thu 11/16/06 | |
Review printed output | GTS,US PD | 1 day | Mon 11/13/06 |
Document requirements for printed output | GTS,US PD | 1 day | Tue 11/14/06 |
Modify printed output to requirements | GTS | 2 days | Thu 11/16/06 |
Usability session (China PD) | 5 days | Fri 11/24/06 | |
Updating | 5 days | Fri 11/24/06 | |
Review | GTS,US PD | 1 day | Mon 11/20/06 |
Suggestions for improvement | GTS,US PD | 1 day | Tue 11/21/06 |
Required changes | GTS,US PD | 1 day | Wed 11/22/06 |
Modify as required if accepted | GTS | 2 days | Fri 11/24/06 |
Output | 4 days | Thu 11/23/06 | |
Review printed output | GTS,US PD | 1 day | Mon 11/20/06 |
Document requirements for printed output | GTS,US PD | 1 day | Tue 11/21/06 |
Modify printed output to requirements | GTS | 2 days | Thu 11/23/06 |
Pricing System | 16 days | Mon 12/4/06 | |
Usability session (US PD) | 5 days | Fri 11/17/06 | |
Updating | 5 days | Fri 11/17/06 | |
Review | GTS,US PD | 1 day | Mon 11/13/06 |
Suggestions for improvement | GTS,US PD | 1 day | Tue 11/14/06 |
Required changes | GTS,US PD | 1 day | Wed 11/15/06 |
Modify as required if accepted | GTS | 2 days | Fri 11/17/06 |
Output | 4 days | Thu 11/16/06 | |
Review printed output | GTS,US PD | 1 day | Mon 11/13/06 |
Document requirements for printed output | GTS,US PD | 1 day | Tue 11/14/06 |
Modify printed output to requirements | GTS | 2 days | Thu 11/16/06 |
Usability session (China PD) | 11 days | Mon 12/4/06 | |
Updating | 11 days | Mon 12/4/06 | |
Review | GTS,US PD | 4 days | Thu 11/23/06 |
Suggestions for improvement | GTS,US PD | 1 day | Fri 11/24/06 |
Required changes | GTS,US PD | 1 day | Mon 11/27/06 |
Modify as required if accepted | GTS | 5 days | Mon 12/4/06 |
Output | 7 days | Tue 11/28/06 | |
Review printed output | GTS,US PD | 2 days | Tue 11/21/06 |
Document requirements for printed output | GTS,US PD | 2 days | Thu 11/23/06 |
Modify printed output to requirements | GTS | 3 days | Tue 11/28/06 |
Quotes and Costing | 15 days | Fri 12/1/06 | |
Usability session (US PD) | 8 days | Wed 11/22/06 | |
Updating | 8 days | Wed 11/22/06 | |
Review | GTS,US PD | 2 days | Tue 11/14/06 |
Suggestions for improvement | GTS,US PD | 2 days | Thu 11/16/06 |
Required changes | GTS,US PD | 1 day | Fri 11/17/06 |
Modify as required if accepted | GTS | 3 days | Wed 11/22/06 |
Output | 4 days | Thu 11/16/06 | |
Review printed output | GTS,US PD | 1 day | Mon 11/13/06 |
Document requirements for printed output | GTS,US PD | 1 day | Tue 11/14/06 |
Modify printed output to requirements | GTS | 2 days | Thu 11/16/06 |
Usability session (China PD) | 7 days | Fri 12/1/06 | |
Updating | 6 days | Thu 11/30/06 | |
Review | GTS,US PD | 2 days | Fri 11/24/06 |
Suggestions for improvement | GTS,US PD | 1 day | Mon 11/27/06 |
Required changes | GTS,US PD | 1 day | Tue 11/28/06 |
Modify as required if accepted | GTS | 2 days | Thu 11/30/06 |
Output | 7 days | Fri 12/1/06 | |
Review printed output | GTS,US PD | 2 days | Fri 11/24/06 |
Document requirements for printed output | GTS,US PD | 2 days | Tue 11/28/06 |
Modify printed output to requirements | GTS | 3 days | Fri 12/1/06 |
Operating Procedures for Style Adoption | 11 days | Mon 11/27/06 | |
Review modifications to UI and Documents | US PD,China Ops,PM,GTS | 2 days | Tue 11/14/06 |
Map and document process flow | US PD,China Ops,PM,GTS | 4 days | Mon 11/20/06 |
China and US sign off on responsibilities. | US PD,China Ops | 0 days | Mon 11/20/06 |
Document procedures | PM | 5 days | Mon 11/27/06 |
Sign off on documentation | US PD,China Ops | 0 days | Mon 11/27/06 |
Implementation | 10 days | Mon 12/11/06 | |
Install selected solution | GTS | 2 days | Wed 11/29/06 |
Conversion | 5 days | Wed 12/6/06 | |
Agree what should be converted | Merch | 3 days | Mon 12/4/06 |
Conversion | GTS | 2 days | Wed 12/6/06 |
Training | GTS,PM,Merch | 2 days | Fri 12/8/06 |
Testing parallel run | Merch,China Ops | 1 day | Mon 12/11/06 |
GO live | 0 days | Mon 12/11/06 | |
Production Tracking | 11 days | Tue 12/26/06 | |
Usability session (China PD) | 11 days | Tue 12/26/06 | |
Updating | 10 days | Mon 12/25/06 | |
Review | China Ops | 4 days | Fri 12/15/06 |
Suggestions for improvement | China Ops | 2 days | Tue 12/19/06 |
Required changes | China Ops | 2 days | Thu 12/21/06 |
Modify as required if accepted | China Ops | 2 days | Mon 12/25/06 |
Output | 11 days | Tue 12/26/06 | |
Review printed output | China Ops | 4 days | Fri 12/15/06 |
Document requirements for printed output | China Ops | 4 days | Thu 12/21/06 |
Modify printed output to requirements | China Ops | 3 days | Tue 12/26/06 |
Usability session (CS) | 6 days | Tue 12/19/06 | |
Output | 6 days | Tue 12/19/06 | |
Review printed output | CS | 2 days | Wed 12/13/06 |
Document requirements for printed output | CS | 2 days | Fri 12/15/06 |
Modify printed output to requirements | CS | 2 days | Tue 12/19/06 |
Operating Procedures for Production Tracking | 11 days | Tue 12/26/06 | |
Review modifications to UI and Documents | US PD,China Ops,PM,GTS | 2 days | Wed 12/13/06 |
Map and document process flow | US PD,China Ops,PM,GTS | 4 days | Tue 12/19/06 |
China and US sign off on responsibilities. | US PD,China Ops | 0 days | Tue 12/19/06 |
Document procedures | PM | 5 days | Tue 12/26/06 |
Sign off on documentation | US PD,China Ops | 0 days | Tue 12/26/06 |
Workflow | 43.5 days | Fri 1/26/07 | |
Development | 32.5 days | Thu 1/11/07 | |
Spec scope of workflow requirements | GTS,PM | 2.5 days | Thu 11/30/06 |
System design | GTS | 5 days | Thu 12/7/06 |
Development | GTS | 20 days | Thu 1/4/07 |
Testing | PM | 5 days | Thu 1/11/07 |
Usability session (China PD) | 11 days | Fri 1/26/07 | |
Updating | 10 days | Thu 1/25/07 | |
Review | China Ops | 4 days | Wed 1/17/07 |
Suggestions for improvement | China Ops | 2 days | Fri 1/19/07 |
Required changes | China Ops | 2 days | Tue 1/23/07 |
Modify as required if accepted | China Ops | 2 days | Thu 1/25/07 |
Output | 11 days | Fri 1/26/07 | |
Review printed output | China Ops | 4 days | Wed 1/17/07 |
Document requirements for printed output | China Ops | 4 days | Tue 1/23/07 |
Modify printed output to requirements | China Ops | 3 days | Fri 1/26/07 |
Usability session (CS) | 6 days | Tue 12/5/06 | |
Output | 6 days | Tue 12/5/06 | |
Review printed output | CS | 2 days | Wed 11/29/06 |
Document requirements for printed output | CS | 2 days | Fri 12/1/06 |
Modify printed output to requirements | CS | 2 days | Tue 12/5/06 |
Operating Procedures for Production Tracking | 11 days | Tue 12/12/06 | |
Review modifications to UI and Documents | US PD,China Ops,PM,GTS | 2 days | Wed 11/29/06 |
Map and document process flow | US PD,China Ops,PM,GTS | 4 days | Tue 12/5/06 |
China and US sign off on responsibilities. | US PD,China Ops | 0 days | Tue 12/5/06 |
Document procedures | PM | 5 days | Tue 12/12/06 |
Sign off on documentation | US PD,China Ops | 0 days | Tue 12/12/06 |